Blacksmith

The Blacksmith Project is located about 70-km north-west of Tom Price and 234km South-West of Port Hedland.

Project Data

  • Location

    Australia

  • Product

    Hematite and Goethite

  • Capacity

    5Mtpa

  • Status

    Scoping

Proposed Development

Significant exploration has been undertaken for the Blacksmith project since 2008. In this time, seven shallow iron ore deposits have been identified, containing significant concentrations of goethite and hematite. 

In May 2024, a pre-feasibility study showed with a high degree of certainty that this project will be able to sustain operations for over 20 years. In this time, it will be able to deliver 5 million tonnes per annum of high-quality direct shipping ore product.

This project is targeting first ore to market in 2025, subject to completion of economic studies, regulatory and third-party approvals, and financing.

Quick Stats

Key highlights of the pre-feasibility study include:

60.5% Fe

Average grade

$523M

NVP 8% (Pre-tax)

3.3 Years

Capital Payback

31%

IPR (Pre-tax)

23 Years

Life of Mine

US $51/t

LOM C1 Cost

$217M

Capital Costs

101Mt

Total LOM Production 

GettyImages-1616028957

Zero Emissions by 2030

Real Zero is our plan to eliminate our scope 1 and scope 2 emissions across our Australian iron ore operations, without voluntary carbon offsets. For the benefit of our planet, our shareholders, and future generations.

Discover Real Zero

Global Operations

Our Metals business includes iron ore operations in the Pilbara and exploration projects across the globe, spanning sites from Australia to Latin America and Gabon.

Our Operations